Monatliche Wartungsarbeiten - kommunales Rechenzentrum

Completed
Scheduled for July 09, 2024 at 4:00 PM – 8:00 PM

Affects

kommunales Rechenzentrum - Hosted Produkte

Under maintenance from 4:00 PM to 8:00 PM

virtueller Arbeitsplatz

Under maintenance from 4:00 PM to 8:00 PM

Hosted Exchange

Under maintenance from 4:00 PM to 8:00 PM

Hosted Mailarchiv

Under maintenance from 4:00 PM to 8:00 PM

SEE Platform

Under maintenance from 4:00 PM to 8:00 PM

Central Administrative Services

Under maintenance from 4:00 PM to 8:00 PM

Updates
  • Completed
    July 09, 2024 at 8:00 PM
    Completed
    July 09, 2024 at 8:00 PM
    Maintenance has completed successfully
  • In progress
    July 09, 2024 at 4:00 PM
    In progress
    July 09, 2024 at 4:00 PM
    Maintenance is now in progress
  • Update
    July 09, 2024 at 4:00 PM
    Planned
    July 09, 2024 at 4:00 PM

    Um die Leistung und Stabilität unserer Systeme weiter zu verbessern, führen wir Wartungsarbeiten durch.

    Standort: VSE.Net & KUES | kommunal

    Die Wartungsarbeiten starten bereits um 14:00 Uhr mit unkritischen Services.

    Zu erwartende Einschränkungen:

    • Es ist keine Einschränkung für Sie als Endkunden zu erwarten.

    Ab 18:00 Uhr weiten wir die Arbeiten auf Hardware-Infrastruktur Services und andere zentrale Komponenten aus.

    Zu erwartende Einschränkungen:

    • Zugriff auf Datenbestände eingeschränkt möglich

    • Es kann zu kurzen Unterbrechungen der Verbindung kommen.

  • Planned
    July 05, 2024 at 8:11 AM
    Planned
    July 05, 2024 at 8:11 AM

    The maintenance window has been postponed to next Tuesday (July 9, 2024) and will only take place in a reduced form.

    We won't start until 6pm and will probably finish by 10pm.